5-stage Clos Example#
Network Diagram#
Assumptions#
- Uplinks from Leaf to Spine are 100G
- Servers can connect at either 10G or 25G
- Support for single-homed or dual-homed servers (only impact is server density)
- Leaf to Spine oversubscription calculations are based on 25G downlink and 100G uplink
- Connections out of the fabric will come via a pair of Leaf nodes (Border Leafs)
- Oversubscription ratio is 1:1 between Spine, Superspine and Border Leaf
- Number of Border Leafs can scale out based on amount of North/South traffic
Details#
Spine node | 7220-IXR-D3 (32xQSFP28 + 2xSFP+) |
Leaf node | 7220-IXR-D2 (48xSFP28+8xQSFP28) |
Border Leaf node | 7220-IXR-D3 (32xQSFP28 + 2xSFP+) |
# of Spines per Pod | 4 |
# of Leafs per Pod | 16 |
# of Pods | 4 |
# of Superspines | 16 |
# of Border Leafs | 2 (or more) |
Max single-homed servers | 3,072 (48*64) |
Max dual-homed servers | 1,536 (48*32) |
Leaf-to-spine oversubscription | 3:1 |